Welcome to the consultation page for the proposed repowering of two wind turbines at Park Farm, Everingham, York, YO42 4LD.

What is the project?

The proposed development is a turbine repowering of 2x WES 250 with 2x Vestas V52 at Park Farm.

Why is this project happening?

Park Farm is a long-established mixed farming business with significant electricity requirements, using approximately 16,000 kWh of electricity each month. To manage the farm’s operations sustainably, it’s important that they improve energy efficiency and make the best use of renewable energy.

The existing two turbines have become very expensive to maintain. The manufacturer has also gone into liquidation, making replacement parts difficult to source. Repowering will deliver more efficient, reliable turbines that are easier to maintain.

Beyond that, repowering provides a more sustainable source of electricity for the future and supports the business's continued operation, maintaining its commitment to responsible farming for years to come.

A Message from the Farm

Our family business has been based here for 90 years, and we are proud to continue farming and contributing to the local community. We run a mixed farming business, producing poultry, beef and arable crops, including wheat, barley and maize for cattle feed. The farm is run by three family members, alongside one employed member of staff.

We are committed to making the farm as efficient and sustainable as possible. In 2016, we invested in 50 kW of solar panels, and renewable energy continues to play an important role in how we manage the business. We want to build on this investment and ensure the farm remains efficient, resilient, and well prepared for the future.

Thank you for taking the time to learn about our plans. We value our local community and want to keep our neighbours informed and involved as we move forward.

-Jonathan Warring

WHO'S INVOLVED?

Cogeo Planning & Environmental Services Ltd.

Consultations providing planning and environmental assessments.

Rengineers B.V

Deployment partner providing refurbished turbines and full support

We’re working together to bring efficient, environmentally responsible and suitable turbines to the site.

Existing Turbines from
Blamire Lane Public Footpath

Proposed Turbines from
Blamire Lane Public Footpath

Existing Turbines
from Bull Lane

Proposed Turbines
from Bull Lane

VISUALISATIONS

VISUALISATIONS

WHATS CHANGING?

We’re proposing replacing the existing turbines with efficient three-bladed models. This will increase the height by 36 metres. One turbine will stay in its current field, while the other will be relocated approximately 425 metres into an adjacent field. We’re changing the position to ensure appropriate separation between the turbines and make sure that the noise levels at the nearest financially involved property meet ETSU-R-97 assessment criteria.

These upgraded turbines will improve energy generation and address the existing maintenance challenges. We designed the final layout to balance the farm's operational requirements with noise considerations and the surrounding landscape.

Turbine Comparison Table

DetailOperational 50kW EnduranceProposed Vestas V27
Hub Height
30m

55m

Rotor Diameter
30m

52m

Tip Height
45m

81m

Access
Existing access track to the turbines

Existing access track to the turbines

Output
250kW each

850kW each

Impact on Nearby Properties

The Cogeo team has completed the screening process. The council has confirmed that this project will not require an EIA application. We are now progressing with the full planning application, which will address all the points raised in the council’s screening process.

What stage is the development at?

We understand how important it is that this project respects nearby residents. Protecting residential amenity has always been one of our top priorities. We have carefully positioned the new turbines to avoid issues like noise or shadow flicker. We also carried out a background noise survey, alongside a detailed noise assessment, to assess noise levels and evaluate the proposal against the ETSU-R-97 assessment criteria. These assessments informed the turbine layout and helped us properly consider potential effects on nearby properties. We’re committed to making sure this repowering fits within the local area and doesn’t affect day-to-day life.

FAQs

Will it be noisy?
No. We understand that noise is a significant concern in these kinds of projects. We have carried out detailed assessments to confirm that noise levels remain within standards.
What will it look like?
The turbines will be 36 metres taller than the existing turbines and will feature a conventional three-bladed design. We’ve produced a photo below to indicate what it will look like.
What happens in extreme weather?
The turbines are designed to automatically shut down during extreme wind speeds. This is a standard safety feature that protects people or property from danger.
Will construction impact traffic?
The turbines will be transported outside of peak traffic times, with transportation specialists managing the process to avoid disruption. The turbines themselves will be built in just two days, with other preparatory works taking place over the six weeks beforehand.

ENQUIRY FORM

This consultation is about keeping our neighbours informed and involved. If you have any questions, feedback or comments about the proposal, we’d love to hear from you.

Please complete the form below. The Project Team will track these comments throughout and provide a response where required.

Thank you again for your interest in the project.

Invalid email address.
Invalid Input
Do you accept the Privacy Statement(*)
Do you accept the Privacy Statement
Please select an option

Form Privacy Statement

By completing this form you are agreeing that we can hold and process your personal data in relation to this consultation exercise.

  • We will only share your personal data with the planning team for planning evaluation purposes only.
  • Your identifiable, personal data will not be used for any other purposes without your consent.